This project included trenching for conduit, applying tape and backfill. Drainage- first entry at catch basin from the parking lot, knock through, install pie, mortar and backfill, Excavating back of building for galleys.

Due to soil conditions and a "dumping ground" of concrete and asphalt--use of the 19,000 LB Hitachi Excavator is required!Galleys, pipe, sump, catch basin, risers installed.